Starting last March, the upgrade of Armadale Road is well underway! The temporary roundabout at Nicholson Road is completed with the Rossiter intersection reaching completion in mid-January.

The Liddelow Road intersection is starting to take shape and a temporary shared path was constructed between Tapper Road and Ghostgum Avenue based on community feedback.

Closer to Peregrine residents, Wright Road is being levelled to stop flooding issues that caused some delays back in 2018. The new roundabout is expected to be completed in February.

In mid-2019, the Armadale and Nicholson Road intersection will upgrade to an east-west bridge, allowing smoother east-west traffic above a roundabout at Nicholson Road.

The new on-off ramp linking Armadale Road with the Kwinana Freeway at North Lake Road is expected to commence construction in the second half of 2019 once the contract has been awarded.

 